Metal Roof with Cathedral Ceiling above Rafters
ICANZ System Reference R0600
Structure
Metal cathedral roof at 22.5o pitch with foil draped over 90mm batten providing 40mm air space with antiglare side of foil facing metal roof. 50mm air space between foil and 10mm plasterboard ceiling fixed between batten and exposed rafter.
Insulation Installation
Option 1: R1.8 roofing blanket adhered to RFL vapour barrier foil product draped over 110mm high battens which are located over ceiling lining and roof rafter. Foil facing downwards to minimum 15mm air space.
Option 2: Double sided antiglare foil over minimum 110mm batten. Remaining 70mm air space below double sided antiglare foil replaced with 20mm air space and R1.5 - 50mm, bulk insulation. Bulk insulation positioned over 10mm plasterboard ceiling fixed between batten and exposed roof rafter.
Option 3: Double sided antiglare foil over minimum 110mm batten. Reflective EPS board positioned at mid height of remaining 70mm air space providing 20mm airspace above and below reflective EPS board.
Option 4: Polyweave or double sided antiglare foil draped over 90mm batten.
NOTE: Total R-Values can be increased by substituting bulk insulation products of higher Material R-Value.